Programme Acceleration for a High-Security Research Facility
Recovering schedule and stakeholder confidence in a nuclear-regulated environment.
Overview
A UK national-security organisation was delivering a major international research facility central to a sovereign capability programme. Significant schedule slippage threatened a critical reputational milestone for senior defence stakeholders, requiring urgent intervention to restore delivery momentum.
The Challenge
The main contractor had fallen substantially behind schedule, preventing timely access for specialist engineering teams. Without rapid recovery, the organisation risked missing a key milestone with implications for stakeholder confidence and international credibility.
Our Approach
We provided hands-on leadership to accelerate programme delivery by:
Leading the client project team and coordinating efforts across multiple partners
Facilitating collaboration between the client, contractor, and supply chain
Prioritising phased handovers of completed areas to allow specialist M&E teams early access and parallel working opportunities
Outcome
Through stronger collaboration and decisive programme management, phased handovers were achieved, momentum was restored, and the organisation successfully protected a key reputational milestone. Stakeholder confidence was reinforced and the project was repositioned for successful completion.
Next Steps
High-security programmes often require rapid, disciplined action to recover lost momentum and safeguard critical milestones. If you need support strengthening governance, accelerating delivery, or restoring stakeholder confidence, we can help.